MCPS’s State School Construction Request Drops to $75.8 Million Before Thursday’s Vote; Eastern Middle Ask Removed

Board of Education meeting

The Montgomery County Public Schools (MCPS) Board of Education is scheduled to vote Thursday, Nov. 19, on a request asking Maryland for $75.815 million in school construction money for fiscal year 2028. The MCPS state request is $9.2 million less than the $85.038 million in Superintendent Thomas W. Taylor’s October recommendation, according to the resolution posted for Thursday’s meeting.

The revised MCPS state request drops the $16.723 million that the October version sought for the replacement of Eastern Middle School. The revised request also raises the state share of the heating, ventilation and air conditioning (HVAC) replacement at Rosa M. Parks Middle School from $10.75 million to $18.25 million, with $15 million of that coming from the state’s Nancy K. Kopp Public School Facilities Priority Fund.

Every dollar in the revised MCPS state request goes to 22 roof, HVAC, fire alarm and restroom projects at named schools, listed in priority order below.

What changed since October

  • Total: $75.815 million, down from $85.038 million in the superintendent’s October recommendation (page 1-12).
  • Eastern Middle School replacement: the October table asked the state for $16.723 million toward the $135.196 million project. The revised table, Attachment B to the resolution, requests no state money for Eastern this year and lists the full $135.196 million under local funds.
  • Rosa M. Parks Middle School HVAC: the estimated cost stays at $21.5 million. The state share requested rises from $10.75 million to $18.25 million, and the local share listed falls from $10.75 million to $3.25 million.
  • Everything else: the other 21 school projects carry the same state amounts in both versions.

The resolution packet for Thursday’s vote does not say why the Eastern Middle School request was removed. The resolution says the plan “maintains the completion dates and project timelines” for Eastern, and a footnote to its project tables says, “There are no Requested changes in major capital project funding or schedules.” MCPS’s October document lists the new Eastern building for August 2030 (page 1-7).

Damascus High School’s replacement, listed at $306.118 million, has no state request in either the October or the November version.

The $15 million from the Kopp Fund

The resolution says “$15 million of the Fiscal Year 2028 State Capital Improvements Program request is to be funded through the Nancy K. Kopp Public School Facilities Priority Fund, a state-established fund created to address critical facility needs in Maryland public schools.” A footnote to Attachment B ties that money to Rosa M. Parks Middle School: “$15 million of the requested State Funding is from the Nancy K. Kopp Public School Facilities Priority Fund. The remaining $3.25 million is from the annual State CIP.”

Advertisement

Advertisement

The state Interagency Commission on School Construction (IAC) says on its Priority Fund page that the fund “was established by the Built to Learn Act and became active for FY 2027” and “will be used to address the most severe issues in a school facility.” The same page says that starting in fiscal 2028 the fund “will fund the highest need projects in the State of Maryland based upon results of the IAC’s Statewide Facilities Assessment.”

The IAC’s procedures guide for the fund’s first year, fiscal 2027, lists a $15 million allocation for Montgomery County, set by the state’s fiscal 2027 capital budget bill and “not subject to local match requirements” (page 2 of the guide). The guide lists air conditioning, heating and roofs among eligible work. Under its schedule, applications are due by Nov. 30, 2026, and the IAC approves projects April 8, 2027 (page 7). The resolution does not say whether the $15 million it requests for Rosa M. Parks Middle School is that fiscal 2027 allocation.

MCPS’s Nov. 2 work-session presentation lists Rosa M. Parks Middle School among the HVAC jobs starting in fiscal 2028, with design followed by three phases of construction (slide 9).

The 22 projects MCPS wants the state to help pay for

MCPS ranks 13 new projects first, followed by nine HVAC projects that already received state money and are listed as cost increases. HVAC work accounts for $64.8 million of the $75.815 million request. Amounts below are the fiscal 2028 state funding requested, from Attachment B of the resolution.

Advertisement

Advertisement

RankSchoolProjectState request
1Springbrook HSHVAC$22,350,000
2Rosa M. Parks MSHVAC$18,250,000
3Dr. Sally K. Ride ESHVAC$5,700,000
4Spark M. Matsunaga ES/Longview SchoolRoof$3,652,000
5Ridgeview MSRoof$3,480,000
6Albert Einstein HSRestrooms$2,300,000
7John T. Baker MSFire alarm$300,000
8Lakelands Park MSFire alarm$300,000
9Bel Pre ESRoof$277,000
10Stedwick ESFire alarm$200,000
11Somerset ESFire alarm$175,000
12Great Seneca ESFire alarm$175,000
13Dr. Charles R. Drew ESRoof$156,000
14A. Mario Loiederman MSHVAC (cost increase)$3,500,000
15Judith A. Resnik ESHVAC (cost increase)$3,175,000
16Dr. Martin Luther King Jr. MSHVAC (cost increase)$2,800,000
17Westland MSHVAC (cost increase)$2,500,000
18Goshen ESHVAC (cost increase)$2,225,000
19New Hampshire Estates ESHVAC (cost increase)$1,675,000
20Strawberry Knoll ESHVAC (cost increase)$1,450,000
21Flower Valley ESHVAC (cost increase)$675,000
22Walt Whitman HSHVAC, phase 3 (cost increase)$500,000
Total$75,815,000
Source: MCPS, “Revised Requested FY 2028 State Capital Improvements Program,” Attachment B, page 5.

For 12 of the 13 new projects, the state amount requested is half of the estimated cost. MCPS’s October document says the state “will pay only 50 percent of eligible state expenses for MCPS projects” (page 1-6). Rosa M. Parks Middle School is the exception among the new projects in the revised table, at $18.25 million of a $21.5 million estimate.

A request, not money in hand

The state does not always fund what MCPS asks for. MCPS’s October document (page 1-5) says the state approved $48.17 million for fiscal 2026 against a $53.32 million request, and $93.67 million for fiscal 2025 against a revised request of $246.3 million. The state approved $49.463 million for MCPS for fiscal 2027, the same page says.

The state request is one part of the resolution. The same resolution asks the county for a $581.6 million fiscal 2028 capital budget appropriation and a $1.879 billion six-year building plan, $25 million more than the plan the County Council approved. The resolution says the plan “restores $23 million to build out a modern, centralized warehouse” and “restores $2 million to explore Public-Private Partnership opportunities for major capital school projects and a consolidated headquarters building.” We reported on MCPS’s current warehouse lease at 750 Progress Way in Gaithersburg on Oct. 12 and Oct. 23. The resolution says it will be sent to the county executive and the County Council.

Rising HVAC costs were also the subject of our Oct. 29 story on MCPS’s estimates for replacing a high school’s system.

The capital budget is item 9.2 on the Board’s Nov. 19 business meeting agenda, in a block of action items scheduled to begin at 5:25 p.m.

Still unanswered

  • Why was the $16.723 million state request for Eastern Middle School removed, and does MCPS plan to ask the state for Eastern money in a later year?
  • Is the $15 million from the Kopp Fund the $15 million fiscal 2027 allocation the state set for Montgomery County, and has MCPS applied for it?
  • If the Kopp money is not awarded, how would MCPS pay for the Rosa M. Parks Middle School HVAC work?

We have not yet put these questions to MCPS; this story will be updated with any response.