The Purple Line’s concessionaire, Purple Line Transit Partners (PLTP), now forecasts that the light rail line will begin carrying passengers on May 27, 2028. That is 149 days after the Dec. 30, 2027 date in its contract, according to the Maryland Transit Administration’s latest construction report to state legislators. MTA says it did not approve that schedule and does not consider the forecast definitive.
Del. Marc Korman (D-Montgomery) shared the report’s key charts on Facebook and wrote that the gap between when the state believes the line will open and the vendor’s date “is growing.” MTA’s own reports, five in a row, show how the concessionaire’s forecast has moved.
How the forecast has moved
| MTA report covers work through | PLTP schedule update | Forecast start of service | Days past Dec. 30, 2027 |
| Jan. 31, 2026 | January 2026 | Feb. 26, 2028 | 58 |
| March 31, 2026 | February 2026 | March 17, 2028 | 78 |
| May 31, 2026 | April 2026 | March 25, 2028 | 86 |
| July 31, 2026 | June 2026 | April 27, 2028 | 119 |
| Sept. 30, 2026 | August 2026 | May 27, 2028 | 149 |
The earlier reports said MTA was reviewing or had reviewed each update. The newest says MTA did not approve the August update, because it does not believe PLTP’s recent schedules accurately reflect past impacts or future opportunities to make up time. MTA wrote that it believes there are still opportunities to finish the remaining work more efficiently and is working with PLTP to shorten the schedule. The report says the contractual date remains Dec. 30, 2027, and its milestone table still lists revenue service as beginning at the end of 2027.
As in earlier reports, the section asking MTA to explain any material change to the project’s cost or schedule says none occurred this period (page 6), while page 7 describes PLTP’s later forecast. MDBayNews reported on that pairing in July. At an Oct. 5 meeting of the Montgomery County Council’s Transportation and Environment Committee, MTA’s Ray Biggs told members the contractual date remains Dec. 30, 2027 and called the actual opening date “dynamic,” WTOP reported.
Progress and cost
The report, which covers work through Sept. 30, puts the project at 93.7% complete, up from 92.1% on July 31. “Startup,” the category that tracks testing and commissioning of train control, power, overhead wire and communications systems, is 55.6% complete, up from 46.9%. MTA says $2.491 billion has been spent on the design-build contract since April 15, 2022, up from $2.421 billion in the previous report.
MTA’s milestone table lists major construction complete in winter 2026-27, the start of end-to-end system testing (trial running) in spring 2027, and the start of revenue service at the end of 2027.
What is happening in Montgomery County
According to the report, live wire testing is finished between Bethesda and Lyttonsville. Overhead wire through downtown Silver Spring along Bonifant Street is complete, and installation has started along Wayne Avenue and Piney Branch Road. Crews finished surface paving and began permanent markings along Wayne Avenue and University Boulevard, and at the Bethesda station they worked on excavation, structural concrete and utilities for the Bethesda South entrance.
The Capital Crescent Trail remains closed. The report lists completion of trail construction as spring 2027; the report covering work through Nov. 30, 2025 listed summer 2026. Paving is done between Bethesda and Connecticut Avenue, and fencing, furnishings, lighting and landscaping remain there before a final inspection with Montgomery County. MTA says sections of the trail may open first for limited access, and that it is working with the county to see whether any part can open before the whole project is finished. At the Oct. 5 committee meeting, WTOP reported, the stretch from Elm Street to Connecticut Avenue was expected to open by spring 2027.
The reports
MTA’s bimonthly reports are filed with the General Assembly’s budget committees. The links below are the state Department of Legislative Services library copies: work through Sept. 30, 2026; July 31; May 31; March 31; Jan. 31; Nov. 30, 2025.
Support local independent news for as little as $5 a month

Recent Posts
- Purple Line Transit Partners Forecast May 2028 Opening, 149 Days Past Contract Date; MTA Did Not Approve Schedule
- 85.5% of Montgomery County Business Locations Have Fewer Than 20 Employees, Census Data Shows
- Live Music This Weekend in Montgomery County: November 27-28
- About 16,700 Montgomery County Customers Still Without Power at 8:45 P.M., With Bethesda Hit Hardest
- About 18,800 Montgomery County Customers Still Without Power, With Rockville and Bethesda Hit Hardest