Montgomery County Public Schools plans to start new heating and cooling (HVAC) replacements at three schools in fiscal 2028: Springbrook High, Rosa M. Parks Middle and Dr. Sally K. Ride Elementary. MCPS says rising costs mean “fewer new projects can be started in FY 2028 as approved funds are needed to complete projects already in progress,” according to slides MCPS staff presented to the Board of Education on Nov. 2.
Nine HVAC projects already in progress need $18.5 million more in state money to cover cost increases, according to the state funding request in the resolution the Board is scheduled to vote on Thursday, Nov. 19.
The same Nov. 2 presentation says MCPS will add 200 school buses in fiscal 2028, growing its fleet from 1,455 buses to about 1,655, with 1,252 parking spaces across its five bus depots.
The HVAC schedule and the bus plan are part of Superintendent Thomas W. Taylor’s recommended fiscal 2028 capital budget and amendments to the six-year capital plan. After the Board votes, the resolution goes to the county executive and the County Council, and the money is not final until the Council approves it.
Three new HVAC projects in fiscal 2028
“The anticipated FY 2027โ2032 HVAC replacement schedule can no longer be accomplished within approved funding levels due to continuing increases in project costs,” MCPS says on slide 8 of the Nov. 2 presentation. MCPS recommends adjusting the HVAC plan “to stay within approved funding levels” and says it “will revisit full six year schedule with FY 2029โ2034 full CIP request next year.”
MCPS’s HVAC Replacement budget in the resolution matches the approved plan: $334.4 million over six years, with $51.425 million to be appropriated for fiscal 2028 (Attachment A).
The HVAC timeline on slide 9 marks three schools as new fiscal 2028 projects:
- Springbrook High: design in summer 2027; the work happens during the 2028-29 school year.
- Rosa M. Parks Middle: design across summers 2027 and 2028; construction in three phases, summers 2029 through 2031.
- Dr. Sally K. Ride Elementary: design across summers 2027 and 2028; construction in two phases, summers 2029 and 2030.
Sherwood High also appears on the timeline, without the fiscal 2028 label: design across summers 2027 and 2028, then the 2029-30 school year “@ Secondary Holding School #1.”
As Moderately MOCO reported Oct. 29, MCPS’s recommended capital plan moves Springbrook High into Thomas S. Wootton High School’s old building for the 2028-29 school year and Sherwood High for 2029-30, so each school’s HVAC can be replaced in one school year instead of in phases over four to five years. The plan’s school pages say each school “will be temporarily relocated to the Secondary Holding School #1, existing Thomas S. Wootton HS, for the duration of the project” (pages 4-89 and 4-115). Wootton High moves from 2100 Wootton Parkway in Rockville to its new building at 9400 Fields Road for the 2027-28 school year (page 4-26).
Springbrook’s HVAC replacement is the No. 1 project on MCPS’s fiscal 2028 state construction request, with a total estimated cost of $44.7 million and $22.35 million requested from the state (Attachment B of the resolution).

Nine HVAC projects need $18.5 million more from the state
MCPS is asking the state for $18.5 million “for cost increases for 9 systemic maintenance projects,” according to the first chapter of the recommended capital plan (page 1-6). The resolution’s state request (Attachment B) lists all nine as HVAC projects, in MCPS’s priority order:
- A. Mario Loiederman Middle: $3.5 million
- Judith A. Resnik Elementary: $3.175 million
- Dr. Martin Luther King Jr. Middle: $2.8 million
- Westland Middle: $2.5 million
- Goshen Elementary: $2.225 million
- New Hampshire Estates Elementary: $1.675 million
- Strawberry Knoll Elementary: $1.45 million
- Flower Valley Elementary: $675,000
- Walt Whitman High (Phase 3): $500,000
The $18.5 million is part of MCPS’s $75.815 million fiscal 2028 state construction request in the resolution, which also asks for $18.25 million for Rosa M. Parks Middle’s HVAC and $5.7 million for Sally K. Ride Elementary’s. A state request is not money in hand; the state decides how much to fund.
200 more buses, 1,252 parking spaces
Our Oct. 29 story on bus parking noted that MCPS’s Oct. 15 presentation did not say how many buses the district expected to add in 2027-28. The Nov. 2 presentation gives the number on slide 19: “Adding 200 new buses to the fleet in FY 2028,” with the total fleet “expected to increase from 1,455 to approximately 1,655.”
“With only 1,252 spaces available across all depots the fleet will be at 403 buses and exceed capacity by 32% for FY 2028,” slide 19 says. MCPS’s projected 1,655 buses minus its 1,252 depot spaces leaves 403 buses without a depot space, 32% more buses than spaces.
MCPS says the fleet has to grow “at least in the short term to support ‘grandfathering’ students for continuity in boundary and program changes,” which it describes as “effectively running double transportation in multiple areas of the district.” Buying the buses is an operating budget cost, the slide says. MCPS repeats that it “will need to utilize its existing properties to park buses in school year 2027โ2028”; the Nov. 2 presentation does not name the properties.
MCPS’s five depots already hold 203 more buses than they have spaces, according to slide 18:
| Depot | Owner | Spaces | Buses | Spaces short |
| Bethesda | Board of Education | 192 | 187 | None (5 open) |
| Clarksburg | Board of Education | 197 | 231 | 34 |
| Randolph | Board of Education | 217 | 245 | 28 |
| Shady Grove | County | 353 | 485 | 132 |
| West Farm | Board of Education | 293 | 307 | 14 |
| Total | 1,252 | 1,455 | 203 (net) |
Of MCPS’s 1,455 buses, 592 are used for special education, according to a note on slide 18.
Shady Grove, the only county-owned depot, is short the most spaces. The county “is supporting lease and build out of new space on East Gude Drive” for heavy maintenance, dispatch offices and training, with “limited bus parking,” MCPS says on slide 20. The Shady Grove site “will be consolidated and shifted to rear of the site; some parking availability will remain as new site cannot accommodate all 500 buses currently at Shady Grove,” slide 20 says; the depot table on slide 18 lists 485 buses at Shady Grove.
For a longer-term fix, MCPS’s Transportation and Regional Support Facilities project has $40 million in the six-year plan, starting with $5 million in fiscal 2030, according to Attachment A of the resolution.
What happens next
- Thursday, Nov. 19: The Board of Education votes on the fiscal 2028 capital budget and amendments to the six-year capital plan (item 9.2, in the action block that starts at 5:25 p.m., on the Board’s agenda).
- After the vote: The resolution goes to the county executive and the County Council, which consider only the amended projects this year.
- Next year: MCPS says it will revisit the full six-year HVAC schedule in its fiscal 2029-2034 capital plan request.
Still unanswered
- Besides Takoma Park Middle School, which MCPS said in October moved from fiscal 2028 to fiscal 2030, which HVAC projects were pushed back to stay within approved funding, and by how long?
- How will Springbrook and Sherwood students get to the Wootton Parkway building, and when will families get details?
- Is the $45 million to $55 million high school HVAC estimate from October based on Springbrook’s design?
- Which MCPS properties will park buses in 2027-28?
We have not yet put these questions to MCPS; this story will be updated with any response.
Support local independent news for as little as $5 a month

Recent Posts
- MCPS Plans Three New HVAC Projects in 2027-28 and a Fleet of 1,655 Buses for 1,252 Spaces
- Takoma Park Police Pension Had 33 Active Officers in July, Down From 38, Actuary Reports
- Strathmore Adds Three New Music Center Performances to 2026-2027 Calendar
- Markoff’s Haunted Forest Ranked No. 1 in the Nation Again, With a Maryland Haunt Right Behind It
- Pop-Up Museum of Kentlands Set for Nov. 22 at The Carriage House