MCPS’s Own Estimate to Replace a High School’s HVAC System Jumped Up to 57% in a Year

Moderately MOCO cover: MCPS high school HVAC costs up to 57%; Wootton old building as swing space; Board votes Nov. 19

Replacing a single high school’s heating and cooling system now costs Montgomery County Public Schools $45 million to $55 million, up from the $30 million to $35 million the district projected a year ago, a 50% to 57% jump, according to a capital budget presentation MCPS administration gave the Board of Education on Oct. 15. The Board held public hearings on the plan Oct. 26 and Oct. 27 and is scheduled to vote on it Nov. 19.

The presentation, delivered by Andrea L. Swiatocha, acting chief of the Division of District Operations, and Donald J. Connelly, director of the Department of Planning and Construction, says on slide 19: “Based on current cost estimates in the last month, a high school HVAC upgrade is now projected to be $45–$55M,” compared with “$30–35M” a year earlier. The figures describe the cost of overhauling one high school’s system, not a total for every high school still waiting on new HVAC; the slide does not name a specific school tied to either estimate.

Slide 19 of MCPS’s Oct. 15, 2026, capital budget presentation to the Board of Education. Highlighting added by Moderately MOCO.
Slide 19 of MCPS’s Oct. 15, 2026, capital budget presentation to the Board of Education. Highlighting added by Moderately MOCO.

A one-year fix instead of four or five, using Wootton’s old building

Alongside the cost estimate, MCPS is proposing to change how it replaces a high school’s HVAC system. Instead of phasing the work over four to five years while students and staff stay in the building, the presentation proposes finishing a full replacement in a single school year by moving that school into swing space, described as “the new Secondary Holding School #1 (existing Thomas S. Wootton HS).” The same slide says this approach “also may be considered in future years for elementary and middle schools.”

As Moderately MOCO reported Oct. 26, MCPS built the $219.3 million Crown High School in Gaithersburg to relieve high school overcrowding, but enrollment projections reversed, and the district now plans to move Wootton into the Crown building, still scheduled to open in August 2027, instead of opening Crown as a 27th high school. Wootton’s existing building on Wootton Parkway becomes available for swing space once Wootton moves out of it and into Crown. MCPS’s recommended capital plan says Springbrook High School would be the first, moving into the old Wootton building for “systemic improvements” during the 2028-29 school year, followed by Sherwood High School in 2029-30. Springbrook’s HVAC replacement is the No. 1 item on MCPS’s state construction funding request, at $44.7 million in total.

Advertisement

Advertisement

MCPS floated a related idea in October 2025, proposing to use the new, not-yet-opened Crown building as a holding school for Damascus, Magruder and Wootton while those schools were renovated, a plan that Bethesda Magazine reported drew competing petitions from Crown-area and Wootton-area families. The Oct. 15, 2026 plan is different: Wootton moves into Crown permanently, and Wootton’s vacated building becomes the holding school instead.

Takoma Park Middle School’s HVAC fix slips two years

The same slide says the cost increases are also changing the district’s six-year HVAC schedule, “particularly for FY 2030 through FY 2032,” and gives one example: “Takoma Park Middle School has moved out from FY 2028 to FY 2030.” Takoma Park Middle School’s HVAC project is now two years behind its earlier schedule, and it is not covered by the new one-year, holding-school approach, since that strategy currently applies only to high schools. A separate slide in the same presentation states the broader effect of the cost increases on the capital program: “Cost increases are reducing scope of work in some projects; fewer HVAC projects can move forward.”

Advertisement

Advertisement

Why it matters in classrooms

Monday’s hearing on the same capital budget document drew testimony about what aging building systems mean day to day. Kim Glassman, the parent of a student at Col. Zadok Magruder High School, told the Board that “Magruder has critical needs now” and that “waiting another decade to start addressing them is equally unacceptable,” adding that at Magruder “the AC randomly goes out, which has led to 86-degree classrooms during AP exams,” Bethesda Magazine reported. For Magruder, this budget round asks for a feasibility study, part of a $2 million facility planning request, not an HVAC replacement, but the testimony speaks to the kind of failure the HVAC program is meant to prevent elsewhere in the district. Board President Grace Rivera-Oven said of the building problems MCPS needs to address, “We’re putting a Band-Aid on a bullet wound,” and “this is an issue that did not just happen overnight,” Bethesda Magazine also reported.

The HVAC increase is part of MCPS’s FY 2028 amendments to its six-year, FY 2027-2032 Capital Improvements Program, a $1.879 billion request that is $25 million above the $1,854,325,000 currently approved, according to the presentation. The County Council approved a $1.85 billion capital budget for MCPS in May, 67% of the $2.78 billion the district had requested, Bethesda Magazine reported.

What happens next

  • Nov. 2: Board work session #2 on the capital budget amendments.
  • Nov. 5: Work session #3, if needed.
  • Nov. 12: A third public hearing, if needed.
  • Nov. 19: Board vote on the FY 2028 capital budget and CIP amendments.

Still unanswered

  • Is the $45 million to $55 million estimate tied to a specific school’s design, or a planning-level figure for any full high school HVAC replacement?
  • Besides Takoma Park Middle School, which other HVAC projects moved on the six-year schedule, and by how long?

We have not yet put these questions to MCPS; this story will be updated with any response.

Updated Oct. 29, 2026, to add which high schools MCPS’s recommended capital plan would move into the old Wootton building first.